In May 2001, the Department of Residential Life was granted approval by the University of Missouri Board of Curators to proceed with implementation of a comprehensive Residential Life Master Plan (RLMP) to upgrade or replace all residence halls at MU. While maintenance within buildings has always been a priority, many residence halls had not seen major renovation since construction; Prior to the Virginia Avenue project, MU's most recently constructed buildings date from the 1960s. The RLMP is being implemented in five phases, each projected to last three to four years.
Phase I projects included the new Virginia Avenue Housing and Dining Facility, which houses 721 students within four new residence halls. The Virginia Avenue complex features a new dining facility and living and learning community support space. Additional Phase I projects addressed Critical Measures improvements within 12 existing residence halls. Critical Measures projects are defined as essential to the preservation of mechanical systems and/or building exteriors-work which is necessary to preserve the useful life of a residence hall until such time as the RLMP phasing schedule allows for full building renovation.

The Plaza 900 dining facility, constructed as part of the Virginia Avenue Housing RLMP project.
Projects associated with Phase II of the RLMP are currently underway. The recently opened 659-bed complex known as Southwest Campus Housing (SWCH) features three new residence halls and support space. Additional Phase II construction includes College Avenue Housing (CAH), the new 345-bed residence hall located on the east side of College Avenue (adjacent to existing Hatch Hall), and the new construction project currently still in design phase, Mid Campus – Defoe/Graham Housing (MCDGH). The Mid Campus complex consists of three new residence halls and will be constructed on the current Baker-Park and Gardner-Hyde residence hall sites. Defoe and Graham Halls will be renovated as a part of this project and a link will be constructed between the two halls. Other Phase II projects include the renovations of Hatch, McDavid, Schurz and Bingham Halls.
Phases III, IV, and V of the RLMP consist of renovations to the remaining residence halls.
Careful attention to building capacity and availability of bed spaces is essential to the success of the RLMP. New construction, necessary to create bed capacity, will allow for the successful renovation of some buildings and removal of those deemed unsuitable for renovation. Each phase of the project is reviewed annually, ensuring the viability of the plan. Careful scrutiny and management of all aspects of the RLMP is essential to the success of this multi-phase project.
| Phase II | |||||||
|---|---|---|---|---|---|---|---|
| Winter 2006 | Summer 2006 | Fall 2006 | Winter 2007 | Summer 2007 | Fall 2007 | Winter 2008 | Fall 2008 |
| Hatch renovation begins | McDavid renovation begins | Southwest Campus Housing project complete College Avenue Housing project complete |
Schurz/Bingham renovation begins | Construction for Mid-Campus Housing begins | Hatch renovation complete McDavid renovation complete |
Defoe/Graham renovation begins | Schurz/Bingham renovation complete |
| Phase III | |||||
|---|---|---|---|---|---|
| Winter 2009 | Fall 2009 | Winter 2010 | Fall 2010 | Winter 2011 | Fall 2011 |
| Hudson renovation begins | Defoe/Graham renovation complete Mid-campus Housing construction complete |
Gillett/Rollins renovation begins | Hudson renovation complete | Mark Twain renovation begins | Gillett/Rollins renovation complete |
| Phase IV | |||||||
|---|---|---|---|---|---|---|---|
| Winter 2012 | Fall 2012 | Winter 2013 | Fall 2013 | Winter 2014 | Fall 2014 | Winter 2015 | Fall 2015 |
| Wolpers renovation begins | Mark Twain renovation complete Pershing renovation complete |
Johnston renovation begins | Wolpers renovation complete | Jones renovation begins | Johnston renovation complete | Lathrop renovation begins | Jones renovation complete |
| Phase V | ||||
|---|---|---|---|---|
| Winter 2016 | Fall 2016 | Fall 2017 | ||
| Laws renovation begins | Lathrop renovation complete | Laws renovation complete | ||
Revised: February 11, 2008

